A D.C. Circuit panel on Friday rejected an environmental challenge to a Tellurian subsidiary's $1.5 billion plan to construct parallel, roughly 30-mile gas pipelines in Louisiana, ruling that federal energy regulators reasonably weighed greenhouse gas impacts and market demand in approving the project.