  1. April 28, 2020

    DC Circ. Won't Revisit Utility's Bid For $38M In Tax Costs

    The D.C. Circuit has refused to revisit its decision that kept in place the Federal Energy Regulatory Commission's denial of Baltimore Gas & Electric Co.'s effort to recover roughly $38 million in tax-related costs from ratepayers despite the utility's claims of unfair treatment.

  2. March 27, 2020

    DC Circ. Won't Let Utility Claw Back $38M In Tax Costs

    The D.C. Circuit on Friday backed the Federal Energy Regulatory Commission's refusal to let Baltimore Gas & Electric Co. recover approximately $38 million in tax-related costs from ratepayers, saying the agency reasonably explained why the Maryland utility's request wasn't consistent with FERC's tax policies.