9th Circ. Says Contractor Properly Axed From Power Plant Job
The Ninth Circuit on Tuesday ruled that a contractor on a Navy power plant project reasonably terminated a subcontractor because of concerns that the work wouldn't be completed on time....To view the full article, register now.