Toshiba Can't Kill $500M Hydro Plant Job Contract Breach Suit
A Michigan federal judge ruled on Wednesday that Toshiba Corp. will not be able to avoid a lawsuit accusing its American unit of performing shoddy work and botching a $500 million contract to overhaul a hydroelectric plant, finding the plant owners plausibly alleged breach of contract and breach of parent guaranty claims.
-
June 27, 2022
Toshiba Defends $500M Hydro Plant Work In Bid To Duck Suit
Toshiba Corp. wants to avoid a suit claiming it turned over shoddy work and missed deadlines overhauling a hydroelectric plant, arguing the work was fine and the allegations fall outside the bounds of the $500 million contract.
-
April 21, 2022
Toshiba Unit Accused Of Botching $500M Hydro Plant Job
The owners of a hydroelectric plant in Michigan have accused a Toshiba Corp. subsidiary of turning over shoddy work and missing key deadlines for a project to overhaul and upgrade the facility despite already pocketing half a billion dollars.